Project Management: Organizational Essential Aspects

Key TopicsMain stages of the project planningWork Breakdown StructureMain instruments of the Project PlanningCommunication ManagementProject Closure

Слайды и текст этой презентации

Слайд 1Project Management: Organizational Essential Aspects
PROJECT MANAGEMENT
Developed by Elizaveta Markovskaya, associate

professor, Phd (Economics)

Project Management: Organizational Essential AspectsPROJECT MANAGEMENTDeveloped by Elizaveta Markovskaya, associate professor, Phd (Economics)

Слайд 2Key Topics
Main stages of the project planning
Work Breakdown Structure
Main instruments

of the Project Planning
Communication Management
Project Closure


Key TopicsMain stages of the project planningWork Breakdown StructureMain instruments of the Project PlanningCommunication ManagementProject Closure

Слайд 3Main stages of the project management planning
Plan of project management

consists of the following elements:
-Plan of the Contracts Management
- Plan

of the Content Management
Plan of the Quality Management
Plan of the Personnel Management
Plan of the Communication Management
Plan of the Schedule Management
Plan of the Value Management
Plan of the Risk Management
Main stages of the project management planning	Plan of project management consists of the following elements:-Plan of the

Слайд 4Main stages of the project management planning
Plan of project management

planning consists of the following stages:

Ideas ‘ creation
Problems’ analysis
Searching for

the alternatives

Evaluation of the alternatives

Forecasting

Main stages of the project management planning	Plan of project management planning consists of the following stages:Ideas ‘

Слайд 5Work Breakdown Structure (WBS)

Work Breakdown Structure means to make the

decomposition of the project on the separated small projects, works

and actions within the task.
For example.
Project – to construct the new scene for the Mariinsky theatre.
What will be the Work Breakdown Structure for these project?

Work Breakdown Structure (WBS)		Work Breakdown Structure means to make the decomposition of the project on the separated

Слайд 6Work Breakdown Structure (WBS). Main Rules.

1. Rule 8/80.
Every task

should be no less than 8 men/hours (1 working day)

and no more than 80 men/ hours (10 working days).
2. Rule of the report period.
The duration of each task should be no more than period in which you are going to organize the meeting dedicated to the projects results. F.e. if you have the meeting every week , the implementation of the task should take no more than 1 week.
Work Breakdown Structure (WBS). Main Rules.		 1. Rule 8/80.	Every task should be no less than 8 men/hours

Слайд 7Work Breakdown Structure (WBS). Main Rules.

3. Rule of the utility.
We

can decompose task on the small actions or steps only

if we can meet the following requirements:
new small tasks or steps can be evaluated easier after the decomposition;
after the decomposition small tasks or steps are shared faster and easier among the personnel;
after the decomposition small tasks are more controllable.
Work Breakdown Structure (WBS). Main Rules.		3. Rule of the utility.	We can decompose task on the small actions

Слайд 8Work Breakdown Structure (WBS). Main Rules.

3. Rule of the utility.
For

example.
The project “Writing the business plan for the investment project

“Zenit-Arena Construction” can be divided by the following steps:
Conception.
Strategy Planning
Functional Analysis (due –diligence)
Planning

Work Breakdown Structure (WBS). Main Rules.		3. Rule of the utility.	For example.	The project “Writing the business plan for

Слайд 9Work Breakdown Structure (WBS). Main Rules.

3. Rule of the utility.
For

example.
The stage “Functional Analysis” can be shared among the following

specialists:
- architects (task – architectural project);
technical specialist (task –cost analysis);
financial specialist (task – calculations) ;
lawer (task – documentation and legal analysis).
Work Breakdown Structure (WBS). Main Rules.		3. Rule of the utility.	For example.	The stage “Functional Analysis” can be shared

Слайд 10Work Breakdown Structure (WBS). Main Rules.

3. Rule of the utility.
For

example.
The stage “Functional Analysis” can be shared among the following

specialists:
- architects (task – architectural project);
technical specialist (task –cost analysis);
financial specialist (task – calculations) ;
lawer (task – documentation and legal analysis).
Work Breakdown Structure (WBS). Main Rules.		3. Rule of the utility.	For example.	The stage “Functional Analysis” can be shared

Слайд 11Main instruments for Project Planning

For the project planning you can

use Microsoft Project.
This program will help you make the project

schedule, to share the tasks among the personnel, to control the deadline of each step.

Home reading. Critical path method
http://en.wikipedia.org/wiki/Critical_path_method

Main instruments for Project Planning		For the project planning you can use Microsoft Project.	This program will help you

Слайд 12Communication Management

Communication is this a process that provides :
Collection
Spreading


Saving
Emission

Information

Communication Management		Communication is this a process that provides :CollectionSpreading  SavingEmission Information

Слайд 13Communication Model


Perception
Decoding
Understanding

Communication Model 		PerceptionDecodingUnderstanding

Слайд 14Communication Plan
Communication Plan consists of the following elements:
Requirements and

Expectations from the Communications
Methods of the Information Exchange
Time and place

for the Communications
Responsibilities



Communication Plan Communication Plan consists of the following elements:Requirements and Expectations from the CommunicationsMethods of the Information

Слайд 15Requirements for the Communications
Every participant should have the following information

about the project:
His responsibilities within the project.
Coordination. The information

plays the coordination role. F. e. the information about the project changes.
Project schedule .



Requirements for the Communications	Every participant should have the following information about the project:His responsibilities within the project.

Слайд 16Requirements for the Communications
4. Decisions made within the projects.


Requirements for the Communications4. Decisions made within the projects.

Слайд 17Thank you for your attention!

Thank you for your attention!

Обратная связь

Если не удалось найти и скачать доклад-презентацию, Вы можете заказать его на нашем сайте. Мы постараемся найти нужный Вам материал и отправим по электронной почте. Не стесняйтесь обращаться к нам, если у вас возникли вопросы или пожелания:

Email: Нажмите что бы посмотреть 

Что такое TheSlide.ru?

Это сайт презентации, докладов, проектов в PowerPoint. Здесь удобно  хранить и делиться своими презентациями с другими пользователями.


Для правообладателей

Яндекс.Метрика